Raiwind Jn. to Nawabshah Jn.
Allama Iqbal Express 10DN — within 15 minutes of the scheduled time 24% of the time, typically 53 minutes late, over 10 days of recorded runs across every stop of its full journey, not this segment alone. That is its whole-journey record, a different promise from this leg alone: over just Raiwind Jn. to Nawabshah Jn. it typically adds 1h 22m, from 33 recorded runs. At Nawabshah Jn. it has typically arrived 136 minutes late, from 44 recorded runs.
Every train, compared
7 of 7 with 7+ daysOver this leg is the CHANGE in a train's delay between Raiwind Jn. and Nawabshah Jn. on the same run — not how late it arrives; a train can run late through its whole journey and still show no change here. — means either too few recorded runs on this leg, or — permanently, for a train whose journey starts right here at Raiwind Jn. — no booked arrival at Raiwind Jn. to measure from at all. Figures cover runs recorded between 30 July 2026 and 4 October 2026. why a delay figure changes along the route.
| Train | Departs | Arrives | Duration | Distance | Typical delay | On-time | Over this leg |
|---|---|---|---|---|---|---|---|
| 38Fareed Express 38DN | 06:55 | 02:02 +1d | 19h 07m | not measured yet | +44 min | 14% | adds 36 min · 27 |
| 2Khyber Mail 2DN | 08:30 +1d | 00:08 +2d | 15h 38m | 939 km | +2h 02m | 7% | adds 1h 12m · 20 |
| 10Allama Iqbal Express 10DN | 13:00 | 03:45 +1d | 14h 45m | 891 km | +53 min | 24% | adds 1h 22m · 33 |
| 8Tezgam 8DN | 14:25 | 04:54 +1d | 14h 29m | 930 km | +58 min | 17% | adds 1h 29m · 36 |
| 34Pak Business 34DN | 17:15 | 06:10 +1d | 12h 55m | 887 km | +1h 05m | 18% | adds 1h 03m · 32 |
| 16Karachi Express 16DN | 18:40 | 08:10 +1d | 13h 30m | 935 km | +2h 05m | 13% | adds 56 min · 36 |
| 14Awam Express 14DN | 19:50 | 13:16 +1d | 17h 26m | 939 km | +2h 09m | 8% | adds 1h 02m · 34 |
What the marks mean
- Departs · Arrives — scheduled local times, published Pakistan Railways timetable
- +1d — a stop on a later day of the train's own run, not a date
- Typical delay · On-time — the train's whole journey, not this segment alone; typical is the median of its recorded stop arrivals, and on-time is within 15 minutes of the scheduled time
- — — fewer than 7 days of recorded runs for that train
- Over this leg — the change in each train's delay between the two stations above, counted on runs recorded at both (a run whose two stations were logged a day apart is matched too, when that day-shifted leg length matches the train's usual one). “adds” means the train picked up extra delay over this stretch; “makes up” means it arrived less late than it left; “no change” means neither. The figure shown is the middle (median) run: no more than half of a train's counted runs did WORSE than it, and no more than half did better — never a claim that exactly half did either, which isn't always possible to state.
- A large “makes up” usually says more about the leg than the train: where several services on this page all recover time, the stretch is booked with room in it. It never means the train ran early — only that it was less late arriving than departing.
- — — in that column: fewer than 7 runs recorded at both stations on the leg's usual booked times, or — permanently, for a train whose journey starts at this page's origin station — no booked arrival there to measure from at all, which will not fill in with more archive age.
Every service in detail
Typical delay and on-time share are the train's whole journey, from 7+ days of recorded runs. Over this leg is the change in that train's delay between the two stations, from runs recorded at both.
- Fareed Express 38DN38فرید ایکسپریس 38 ڈائون06:55→02:02 +1d19h 07m14% on time · +44 minadds 36 min over this leg · 27 runs
- Khyber Mail 2DN2خیبر میل 2 ڈائون08:30 +1d→00:08 +2d15h 38m7% on time · +2h 02madds 1h 12m over this leg · 20 runs
- Allama Iqbal Express 10DN10علامہ اقبال ایکسپریس 10 ڈائون13:00→03:45 +1d14h 45m24% on time · +53 minadds 1h 22m over this leg · 33 runs
- Tezgam 8DN8تیزگام 8 ڈاؤن14:25→04:54 +1d14h 29m17% on time · +58 minadds 1h 29m over this leg · 36 runs
- Pak Business 34DN34پاک بزنس 34 ڈائون17:15→06:10 +1d12h 55m18% on time · +1h 05madds 1h 03m over this leg · 32 runs
- Karachi Express 16DN16کراچی ایکسپریس 16 ڈائون18:40→08:10 +1d13h 30m13% on time · +2h 05madds 56 min over this leg · 36 runs
- Awam Express 14DN14عوام ایکسپریس 14 ڈائون19:50→13:16 +1d17h 26m8% on time · +2h 09madds 1h 02m over this leg · 34 runs
Travelling the other way? Nawabshah Jn. to Raiwind Jn. trains →
Common questions
How many trains run from Raiwind Jn. to Nawabshah Jn.?
7 scheduled services on the current published timetable. That is what is booked to run, not what ran today.
Which is the fastest train from Raiwind Jn. to Nawabshah Jn.?
Pak Business 34DN, booked at 12h 55m for the journey. That is the timetable's figure. Whether it holds on the day is what the delay columns describe.
Which train from Raiwind Jn. to Nawabshah Jn. is most likely to be on time?
Allama Iqbal Express 10DN has the best recorded punctuality of the services we hold enough history for: 24% of its recorded stop arrivals were within 15 minutes of schedule, with a typical delay of 53 min. That is its record across every stop of its full journey, not this leg alone. Measured from recorded runs, not from the timetable. 7 of 7 services on this route currently have enough recorded history to rank at all.
Is there an overnight train from Raiwind Jn. to Nawabshah Jn.?
Yes. All 7 scheduled services are booked to arrive on a later day than they depart: Fareed Express 38DN, Khyber Mail 2DN, Allama Iqbal Express 10DN, Tezgam 8DN and others.
Do trains lose time between Raiwind Jn. and Nawabshah Jn.?
Typically yes. Tezgam 8DN adds about 1h 29m to its delay over this leg, measured across 36 recorded runs. That is the CHANGE over the leg, not how late the train arrives: a train can run late its whole journey and add nothing here.
How far is it from Raiwind Jn. to Nawabshah Jn. by train?
It is between 887 and 939 km along the track, depending on the service. Measured by summing our own GPS traces of trains running the route, not the straight-line distance between the two stations, which is always shorter than the rails. That is measured on 6 of the 7 services; the rest of the track on this route has not been traced yet.
Are these Raiwind Jn. to Nawabshah Jn. timings the real arrival times?
No. The departure and arrival columns are what the published timetable books. The delay columns beside them are what we recorded actually happening, from the operator's own reports and from GPS traces of the trains. Where a delay figure is blank we do not yet hold enough recorded runs to publish one.