The ranking

within 15 min
#TrainOn timeUsually lateBad dayDays
1203Jand Passenger 203up100%+4 min+9 min7
2210Faiz Ahmad Faiz Passenger 210DN91%+5 min+15 min22
3134Kohat Express 134DN86%+2 min+19 min10
4202Attock Passenger 202dn83%+8 min+18 min7
5225Shaheen Passenger 225UP82%8 min early+2h 38m8
6133Kohat Express 133UP82%+7 min+37 min9
7108Islamabad Express 108DN62%+8 min+54 min23
8212Narowal Passenger 212DN52%+15 min+42 min25
9146Sukkur Express 146DN49%+16 min+1h 17m25
10103Subak Kharam 103UP47%+17 min+1h 18m23
11116Musa Pak Express 116DN46%+17 min+38 min25
12151Shah Latif Express 151UP43%+24 min+1h 29m20
13106Rawal Express 106DN42%+27 min+1h 02m21
14126Lasani Express 126DN40%+18 min+37 min19
1528Shalimar Express 28DN39%+27 min+2h 03m26
16101Subak Raftar 101UP39%+22 min+1h 12m23
176Green Line 6DN36%+56 min+2h 51m25
18105Rawal Express 105UP35%+30 min+1h 03m23
19128Mehr Express 128DN35%+31 min+1h 19m24
20107Islamabad Express 107UP32%+1h 08m+2h 08m23
2118Millat Express 18DN30%+1h 04m+3h 28m26
22Karachi Circular Railway 1up29%+31 min+1h 05m21
23125Lasani Express 125UP29%+35 min+1h 21m20
2410Allama Iqbal Express 10DN28%+43 min+2h 20m26
25115Musa Pak Express 115UP27%+33 min+1h 40m25
26147Mianwali Express 147UP27%+26 min+1h 32m24
27102Subak Raftar 102DN26%+29 min+1h 17m25
28267Rawalpindi Passenger 267UP25%+29 min+56 min24
295Green Line 5UP24%+50 min+2h 43m25
30140Sandal Express 140Dn24%+40 min+1h9
3140Jaffar Express 40DN20%+50 min+1h 31m26
32148Mianwali Express 148DN20%+2h 09m+4h 06m22
33104Subak Kharam 104DN20%+45 min+1h 25m22
3442Karakoram Express 42DN19%+1h 36m+4h 32m24
35172Sialkot Express 172Dn18%+37 min+1h 03m21
368Tezgam 8DN16%+1h 09m+3h 45m26
3738Fareed Express 38DN16%+1h 06m+2h 35m24
3814Awam Express 14DN15%+1h 20m+3h 12m26
3912Hazara Express 12DN14%+1h 35m+3h 48m25
40127Mehr Express 127UP14%+42 min+1h 24m22
41145Sukkur Express 145UP13%+1h 40m+3h 07m25
4213Awam Express 13UP13%+1h 32m+4h 37m26
43139Sandal Express 139Up12%+33 min+1h 04m8
4411Hazara Express 11UP10%+1h 35m+4h 32m26
4548Rehman Baba Express 48DN10%+2h 24m+4h 42m26
46258Bhullhe Shah passenger 258Dn10%+1h 27m+2h 41m23
47171Sialkot Express 171Up10%+41 min+1h 04m22
4826Bahauddin Zikria Express 26DN10%+1h 29m+4h 17m24
49130Thall Express 130DN9%+39 min+1h 08m13
5027Shalimar Express 27UP9%+1h 52m+5h 30m26
5147Rehman Baba Express 47UP9%+1h 41m+3h 57m26
5234Pak Business 34DN9%+2h 28m+5h 27m22
53257Bhullhe Shah passenger 257Up8%+35 min+1h 55m13
5415Karachi Express 15UP8%+1h 48m+3h 25m24
55211Narowal Passenger 211UP8%+2h 05m+2h 45m26
5617Millat Express 17UP8%+1h 40m+4h 39m25
5737Fareed Express 37UP8%+1h 47m+5h 34m23
5816Karachi Express 16DN8%+2h 40m+5h 43m25
5933Pak Business 33UP8%+2h 59m+5h 33m23
602Khyber Mail 2DN7%+2h+3h 10m25
6141Karakoram Express 41UP7%+2h 27m+5h 02m24
62Karachi Circular Railway 2dn6%+1h 10m+1h 52m22
63209Faiz Ahmad Faiz Passenger 209UP6%+1h 27m+2h 10m20
64129Thall Express 129UP6%+1h 09m+1h 48m11
6525Bahauddin Zikria Express 25UP5%+1h 46m+4h 15m23
66152Shah Latif Express 152DN5%+1h 45m+3h 02m19
677Tezgam 7UP4%+2h 08m+4h 51m24
68227Dgk Shuttle 227UP4%+44 min+1h 21m20
6946Pakistan Express 46DN4%+2h 27m+4h 45m24
701Khyber Mail 1UP3%+2h 19m+4h 59m25
719Allama Iqbal Express 9UP3%+2h 49m+6h 09m25
72228Dgk Shuttle 228DN2%+1h 07m+1h 47m21
7339Jaffar Express 39UP2%+1h 43m+3h 36m25
74226Shaheen Passenger 226DN1%+2h 35m+4h 04m17
7545Pakistan Express 45UP1%+4h 39m+6h 35m25
76205Babu passenger 205 up0%+49 min+2h13
77206Babu passenger 206 dn0%+1h 14m+2h 03m14
78268Rawalpindi Passenger 268DN0%+4h 15m+5h 55m14

What each column means

  • On time — share of stops reached within 15 minutes of the scheduled time, across a rolling window of recent runs.
  • Usually late — the median delay at a stop over the same window: half of recorded stops were later than this. A negative figure means the train typically ran early.
  • Bad day — the 90th percentile of recorded stop arrivals: worse than nine tenths of them.
  • Days — days of recorded runs behind the row. A train enters the table at 7 days.
  • — — no figure yet for that column.
  • Where these figures come from, and what we do and do not measure, is set out in full on how this site works, and in what on time means here, and every threshold behind it.

Passenger services only; light-engine and shunting movements run to no timetable. Times are Pakistan Standard Time. 78 services past 7 days so far.

Common questions

Which is the most punctual train in Pakistan?

Jand Passenger 203up, of the 78 passenger services with enough recorded history to rank: 100% of its recorded arrivals were within 15 minutes of schedule, with a typical delay of +4 min. Measured from arrivals we recorded, not from the timetable.

Which Pakistan Railways train runs late most often?

Of the 78 services ranked here, Rawalpindi Passenger 268DN has the lowest on-time rate: 0% of its recorded arrivals were within 15 minutes of schedule, with a typical delay of +4h 15m. That is the worst record among the services we hold enough history for, which is not the same as the worst on the network: a service we have not recorded for 7 days does not appear in this table at all.

How is this punctuality ranking calculated?

By the share of a service's recorded arrivals that landed within 15 minutes of the booked time, across its last 28 days of running, counting every stop on the route rather than only the final one. Services level on that are separated by their typical delay, lowest first. Nothing here is modelled or predicted.

Why is my train missing from the rankings?

Because we do not yet hold 7 days of recorded running for it. A service ranked on two days of history would move several places on the strength of one bad afternoon, so it waits instead. 78 services have cleared that bar so far, and the rest appear as the archive fills. Every train has its own page with whatever we do hold, ranked or not.