Jaffar Express 40DN — within 15 minutes of the scheduled time 20% of the time, typically 50 minutes late, over 26 days of recorded runs across every stop of its full journey, not this segment alone. That is its whole-journey record, a different promise from this leg alone: over just Rawalpindi to Ghotki it typically adds 1h 16m, from 38 recorded runs. At Ghotki it has typically arrived 94 minutes late, from 74 recorded runs.
Every train, compared
7 of 7 with 7+ daysOver this leg is the CHANGE in a train's delay between Rawalpindi and Ghotki on the same run — not how late it arrives; a train can run late through its whole journey and still show no change here. — means either too few recorded runs on this leg, or — permanently, for a train whose journey starts right here at Rawalpindi — no booked arrival at Rawalpindi to measure from at all. Figures cover runs recorded between 30 July 2026 and 18 November 2026. why a delay figure changes along the route.
| Train | Departs | Arrives | Duration | Typical delay | On-time | Over this leg |
|---|---|---|---|---|---|---|
| 2Khyber Mail 2DN | 02:00 +1d | 20:10 +1d | 18h 10m | +2h | 7% | adds 2h 49m · 10 |
| 46Pakistan Express 46DN | 06:00 | 22:54 | 16h 54m | +2h 27m | 4% | no data |
| 8Tezgam 8DN | 08:00 | 00:23 +1d | 16h 23m | +1h 09m | 16% | no data |
| 40Jaffar Express 40DN | 09:35 | 02:13 +1d | 16h 38m | +50 min | 20% | adds 1h 16m · 38 |
| 14Awam Express 14DN | 12:30 | 07:30 +1d | 19h | +1h 20m | 15% | adds 1h 59m · 55 |
| 48Rehman Baba Express 48DN | 14:40 | 06:24 +1d | 15h 44m | +2h 24m | 10% | adds 2h 32m · 48 |
| 12Hazara Express 12DN | 17:10 | 13:36 +1d | 20h 26m | +1h 35m | 14% | adds 1h 45m · 45 |
What the marks mean
- Departs · Arrives — scheduled local times, published Pakistan Railways timetable
- +1d — a stop on a later day of the train's own run, not a date
- Typical delay · On-time — the train's whole journey, not this segment alone; typical is the median of its recorded stop arrivals, and on-time is within 15 minutes of the scheduled time
- — — fewer than 7 days of recorded runs for that train
- Over this leg — the change in each train's delay between the two stations above, counted on runs recorded at both (a run whose two stations were logged a day apart is matched too, when that day-shifted leg length matches the train's usual one). “adds” means the train picked up extra delay over this stretch; “makes up” means it arrived less late than it left; “no change” means neither. The figure shown is the middle (median) run: no more than half of a train's counted runs did WORSE than it, and no more than half did better — never a claim that exactly half did either, which isn't always possible to state.
- A large “makes up” usually says more about the leg than the train: where several services on this page all recover time, the stretch is booked with room in it. It never means the train ran early — only that it was less late arriving than departing.
- — — in that column: fewer than 7 runs recorded at both stations on the leg's usual booked times, or — permanently, for a train whose journey starts at this page's origin station — no booked arrival there to measure from at all, which will not fill in with more archive age.
Every service in detail
Typical delay and on-time share are the train's whole journey, from 7+ days of recorded runs. Over this leg is the change in that train's delay between the two stations, from runs recorded at both.
- Khyber Mail 2DN2خیبر میل 2 ڈائون02:00 +1d→20:10 +1d18h 10m7% on time · +2hadds 2h 49m over this leg · 10 runs
- Pakistan Express 46DN46پاکستان ایکسپریس 46 ڈائون06:00→22:5416h 54m4% on time · +2h 27mno data over this leg
- Tezgam 8DN8تیزگام 8 ڈاؤن08:00→00:23 +1d16h 23m16% on time · +1h 09mno data over this leg
- Jaffar Express 40DN40جعفر ایکسپریس 40 ڈائون09:35→02:13 +1d16h 38m20% on time · +50 minadds 1h 16m over this leg · 38 runs
- Awam Express 14DN14عوام ایکسپریس 14 ڈائون12:30→07:30 +1d19h15% on time · +1h 20madds 1h 59m over this leg · 55 runs
- Rehman Baba Express 48DN48رحمان بابا ایکسپریس 48 ڈاؤن14:40→06:24 +1d15h 44m10% on time · +2h 24madds 2h 32m over this leg · 48 runs
- Hazara Express 12DN12ہزارا ایکسپریس 12ڈاؤن17:10→13:36 +1d20h 26m14% on time · +1h 35madds 1h 45m over this leg · 45 runs
Travelling the other way? Ghotki to Rawalpindi trains →
Common questions
How many trains run from Rawalpindi to Ghotki?
7 scheduled services on the current published timetable. That is what is booked to run, not what ran today.
Which is the fastest train from Rawalpindi to Ghotki?
Rehman Baba Express 48DN, booked at 15h 44m for the journey. That is the timetable's figure. Whether it holds on the day is what the delay columns describe.
Which train from Rawalpindi to Ghotki is most likely to be on time?
Jaffar Express 40DN has the best recorded punctuality of the services we hold enough history for: 20% of its recorded stop arrivals were within 15 minutes of schedule, with a typical delay of 50 min. That is its record across every stop of its full journey, not this leg alone. Measured from recorded runs, not from the timetable. 7 of 7 services on this route currently have enough recorded history to rank at all.
Is there an overnight train from Rawalpindi to Ghotki?
Yes. 5 of the 7 scheduled services are booked to arrive on a later day than they depart: Tezgam 8DN, Jaffar Express 40DN, Awam Express 14DN, Rehman Baba Express 48DN and others.
Do trains lose time between Rawalpindi and Ghotki?
Typically yes. Khyber Mail 2DN adds about 2h 49m to its delay over this leg, measured across 10 recorded runs. That is the CHANGE over the leg, not how late the train arrives: a train can run late its whole journey and add nothing here.
Are these Rawalpindi to Ghotki timings the real arrival times?
No. The departure and arrival columns are what the published timetable books. The delay columns beside them are what we recorded actually happening, from the operator's own reports and from GPS traces of the trains. Where a delay figure is blank we do not yet hold enough recorded runs to publish one.