Khanpur Jn. to Tando Adam
Allama Iqbal Express 10DN — within 15 minutes of the scheduled time 24% of the time, typically 71 minutes late, over 7 days of recorded runs across every stop of its full journey, not this segment alone. That is its whole-journey record, a different promise from this leg alone: over just Khanpur Jn. to Tando Adam it typically adds 44 min, from 35 recorded runs. At Tando Adam it has typically arrived 123 minutes late, from 39 recorded runs.
Every train, compared
4 of 7 with 7+ daysOver this leg is the CHANGE in a train's delay between Khanpur Jn. and Tando Adam on the same run — not how late it arrives; a train can run late through its whole journey and still show no change here. — means either too few recorded runs on this leg, or — permanently, for a train whose journey starts right here at Khanpur Jn. — no booked arrival at Khanpur Jn. to measure from at all. Figures cover runs recorded between 30 July 2026 and 6 September 2026. why a delay figure changes along the route.
| Train | Departs | Arrives | Duration | Distance | Typical delay | On-time | Over this leg |
|---|---|---|---|---|---|---|---|
| 14Awam Express 14DN | 05:00 +1d | 14:57 +1d | 9h 57m | 464 km | +2h 14m | 8% | adds 18 min · 38 |
| 12Hazara Express 12DN | 10:55 +1d | 20:11 +1d | 9h 16m | 465 km | — | — | makes up 19 min · 34 |
| 38Fareed Express 38DN | 18:55 | 03:35 +1d | 8h 40m | not measured yet | +44 min | 16% | makes up 2 min · 29 |
| 26Bahauddin Zikria Express 26DN | 20:05 | 04:22 +1d | 8h 17m | 464 km | — | — | adds 23 min · 22 |
| 46Pakistan Express 46DN | 20:40 | 04:38 +1d | 7h 58m | 463 km | +1h 04m | 4% | adds 54 min · 36 |
| 10Allama Iqbal Express 10DN | 21:00 | 05:07 +1d | 8h 07m | 464 km | +1h 11m | 24% | adds 44 min · 35 |
| 8Tezgam 8DN | 22:15 | 06:22 +1d | 8h 07m | 461 km | — | — | adds 49 min · 37 |
What the marks mean
- Departs · Arrives — scheduled local times, published Pakistan Railways timetable
- +1d — a stop on a later day of the train's own run, not a date
- Typical delay · On-time — the train's whole journey, not this segment alone; typical is the median of its recorded stop arrivals, and on-time is within 15 minutes of the scheduled time
- — — fewer than 7 days of recorded runs for that train
- Over this leg — the change in each train's delay between the two stations above, counted on runs recorded at both (a run whose two stations were logged a day apart is matched too, when that day-shifted leg length matches the train's usual one). “adds” means the train picked up extra delay over this stretch; “makes up” means it arrived less late than it left; “no change” means neither. The figure shown is the middle (median) run: no more than half of a train's counted runs did WORSE than it, and no more than half did better — never a claim that exactly half did either, which isn't always possible to state.
- A large “makes up” usually says more about the leg than the train: where several services on this page all recover time, the stretch is booked with room in it. It never means the train ran early — only that it was less late arriving than departing.
- — — in that column: fewer than 7 runs recorded at both stations on the leg's usual booked times, or — permanently, for a train whose journey starts at this page's origin station — no booked arrival there to measure from at all, which will not fill in with more archive age.
Every service in detail
Typical delay and on-time share are the train's whole journey, from 7+ days of recorded runs. Over this leg is the change in that train's delay between the two stations, from runs recorded at both.
- Awam Express 14DN14عوام ایکسپریس 14 ڈائون05:00 +1d→14:57 +1d9h 57m8% on time · +2h 14madds 18 min over this leg · 38 runs
- Hazara Express 12DN12ہزارا ایکسپریس 12ڈاؤن10:55 +1d→20:11 +1d9h 16mno delay figure yetmakes up 19 min over this leg · 34 runs
- Fareed Express 38DN38فرید ایکسپریس 38 ڈائون18:55→03:35 +1d8h 40m16% on time · +44 minmakes up 2 min over this leg · 29 runs
- Bahauddin Zikria Express 26DN26بہائو الدین زکریا ایکسپریس26 ڈائون20:05→04:22 +1d8h 17mno delay figure yetadds 23 min over this leg · 22 runs
- Pakistan Express 46DN46پاکستان ایکسپریس 46 ڈائون20:40→04:38 +1d7h 58m4% on time · +1h 04madds 54 min over this leg · 36 runs
- Allama Iqbal Express 10DN10علامہ اقبال ایکسپریس 10 ڈائون21:00→05:07 +1d8h 07m24% on time · +1h 11madds 44 min over this leg · 35 runs
- Tezgam 8DN8تیزگام 8 ڈاؤن22:15→06:22 +1d8h 07mno delay figure yetadds 49 min over this leg · 37 runs
Travelling the other way? Tando Adam to Khanpur Jn. trains →
Common questions
How many trains run from Khanpur Jn. to Tando Adam?
7 scheduled services on the current published timetable. That is what is booked to run, not what ran today.
Which is the fastest train from Khanpur Jn. to Tando Adam?
Pakistan Express 46DN, booked at 7h 58m for the journey. That is the timetable's figure. Whether it holds on the day is what the delay columns describe.
Which train from Khanpur Jn. to Tando Adam is most likely to be on time?
Allama Iqbal Express 10DN has the best recorded punctuality of the services we hold enough history for: 24% of its recorded stop arrivals were within 15 minutes of schedule, with a typical delay of 1h 11m. That is its record across every stop of its full journey, not this leg alone. Measured from recorded runs, not from the timetable. 4 of 7 services on this route currently have enough recorded history to rank at all.
Is there an overnight train from Khanpur Jn. to Tando Adam?
Yes. 5 of the 7 scheduled services are booked to arrive on a later day than they depart: Fareed Express 38DN, Bahauddin Zikria Express 26DN, Pakistan Express 46DN, Allama Iqbal Express 10DN and others.
Do trains lose time between Khanpur Jn. and Tando Adam?
Typically yes. Pakistan Express 46DN adds about 54 min to its delay over this leg, measured across 36 recorded runs. That is the CHANGE over the leg, not how late the train arrives: a train can run late its whole journey and add nothing here.
How far is it from Khanpur Jn. to Tando Adam by train?
It is between 461 and 465 km along the track, depending on the service. Measured by summing our own GPS traces of trains running the route, not the straight-line distance between the two stations, which is always shorter than the rails. That is measured on 6 of the 7 services; the rest of the track on this route has not been traced yet.
Are these Khanpur Jn. to Tando Adam timings the real arrival times?
No. The departure and arrival columns are what the published timetable books. The delay columns beside them are what we recorded actually happening, from the operator's own reports and from GPS traces of the trains. Where a delay figure is blank we do not yet hold enough recorded runs to publish one.