Rahim Yar Khan to Rohri Jn.
Shalimar Express 28DN — within 15 minutes of the scheduled time 39% of the time, typically 27 minutes late, over 7 days of recorded runs across every stop of its full journey, not this segment alone. That is its whole-journey record, a different promise from this leg alone: over just Rahim Yar Khan to Rohri Jn. it typically adds 3 min, from 23 recorded runs. At Rohri Jn. it has typically arrived 16 minutes late, from 31 recorded runs.
Every train, compared
9 of 13 with 7+ daysOver this leg is the CHANGE in a train's delay between Rahim Yar Khan and Rohri Jn. on the same run — not how late it arrives; a train can run late through its whole journey and still show no change here. — means either too few recorded runs on this leg, or — permanently, for a train whose journey starts right here at Rahim Yar Khan — no booked arrival at Rahim Yar Khan to measure from at all. Figures cover runs recorded between 30 July 2026 and 4 October 2026. why a delay figure changes along the route.
| Train | Departs | Arrives | Duration | Distance | Typical delay | On-time | Over this leg |
|---|---|---|---|---|---|---|---|
| 34Pak Business 34DN | 00:19 +1d | 03:00 +1d | 2h 41m | 173 km | — | — | adds 2 min · 36 |
| 18Millat Express 18DN | 01:06 +1d | 03:55 +1d | 2h 49m | 175 km | +2h 35m | 8% | adds 6 min · 38 |
| 40Jaffar Express 40DN | 01:54 +1d | 04:45 +1d | 2h 51m | 175 km | +1h | 24% | adds 11 min · 18 |
| 48Rehman Baba Express 48DN | 04:51 +1d | 07:40 +1d | 2h 49m | 175 km | +1h 56m | 14% | adds 16 min · 37 |
| 14Awam Express 14DN | 05:34 +1d | 08:55 +1d | 3h 21m | 175 km | +2h 14m | 8% | makes up 3 min · 36 |
| 12Hazara Express 12DN | 11:35 +1d | 14:55 +1d | 3h 20m | 175 km | — | — | makes up 16 min · 35 |
| 28Shalimar Express 28DN | 16:42 | 19:10 | 2h 28m | not measured yet | +27 min | 39% | adds 3 min · 23 |
| 2Khyber Mail 2DN | 18:04 +1d | 21:10 +1d | 3h 06m | 175 km | +2h 12m | 8% | adds 8 min · 20 |
| 38Fareed Express 38DN | 19:29 | 22:35 | 3h 06m | not measured yet | +44 min | 16% | makes up 8 min · 29 |
| 26Bahauddin Zikria Express 26DN | 20:39 | 23:35 | 2h 56m | 175 km | — | — | adds 1 min · 21 |
| 46Pakistan Express 46DN | 21:14 | 00:10 +1d | 2h 56m | 175 km | +1h 04m | 4% | adds 4 min · 37 |
| 10Allama Iqbal Express 10DN | 21:34 | 00:25 +1d | 2h 51m | 175 km | +1h 11m | 24% | adds 9 min · 35 |
| 8Tezgam 8DN | 22:49 | 01:30 +1d | 2h 41m | 173 km | — | — | adds 16 min · 37 |
What the marks mean
- Departs · Arrives — scheduled local times, published Pakistan Railways timetable
- +1d — a stop on a later day of the train's own run, not a date
- Typical delay · On-time — the train's whole journey, not this segment alone; typical is the median of its recorded stop arrivals, and on-time is within 15 minutes of the scheduled time
- — — fewer than 7 days of recorded runs for that train
- Over this leg — the change in each train's delay between the two stations above, counted on runs recorded at both (a run whose two stations were logged a day apart is matched too, when that day-shifted leg length matches the train's usual one). “adds” means the train picked up extra delay over this stretch; “makes up” means it arrived less late than it left; “no change” means neither. The figure shown is the middle (median) run: no more than half of a train's counted runs did WORSE than it, and no more than half did better — never a claim that exactly half did either, which isn't always possible to state.
- A large “makes up” usually says more about the leg than the train: where several services on this page all recover time, the stretch is booked with room in it. It never means the train ran early — only that it was less late arriving than departing.
- — — in that column: fewer than 7 runs recorded at both stations on the leg's usual booked times, or — permanently, for a train whose journey starts at this page's origin station — no booked arrival there to measure from at all, which will not fill in with more archive age.
Every service in detail
Typical delay and on-time share are the train's whole journey, from 7+ days of recorded runs. Over this leg is the change in that train's delay between the two stations, from runs recorded at both.
- Pak Business 34DN34پاک بزنس 34 ڈائون00:19 +1d→03:00 +1d2h 41mno delay figure yetadds 2 min over this leg · 36 runs
- Millat Express 18DN18ملت ایکسپریس 18 ڈائون01:06 +1d→03:55 +1d2h 49m8% on time · +2h 35madds 6 min over this leg · 38 runs
- Jaffar Express 40DN40جعفر ایکسپریس 40 ڈائون01:54 +1d→04:45 +1d2h 51m24% on time · +1hadds 11 min over this leg · 18 runs
- Rehman Baba Express 48DN48رحمان بابا ایکسپریس 48 ڈاؤن04:51 +1d→07:40 +1d2h 49m14% on time · +1h 56madds 16 min over this leg · 37 runs
- Awam Express 14DN14عوام ایکسپریس 14 ڈائون05:34 +1d→08:55 +1d3h 21m8% on time · +2h 14mmakes up 3 min over this leg · 36 runs
- Hazara Express 12DN12ہزارا ایکسپریس 12ڈاؤن11:35 +1d→14:55 +1d3h 20mno delay figure yetmakes up 16 min over this leg · 35 runs
- Shalimar Express 28DN28شالیمار ایکسپریس 28 ڈائون16:42→19:102h 28m39% on time · +27 minadds 3 min over this leg · 23 runs
- Khyber Mail 2DN2خیبر میل 2 ڈائون18:04 +1d→21:10 +1d3h 06m8% on time · +2h 12madds 8 min over this leg · 20 runs
- Fareed Express 38DN38فرید ایکسپریس 38 ڈائون19:29→22:353h 06m16% on time · +44 minmakes up 8 min over this leg · 29 runs
- Bahauddin Zikria Express 26DN26بہائو الدین زکریا ایکسپریس26 ڈائون20:39→23:352h 56mno delay figure yetadds 1 min over this leg · 21 runs
- Pakistan Express 46DN46پاکستان ایکسپریس 46 ڈائون21:14→00:10 +1d2h 56m4% on time · +1h 04madds 4 min over this leg · 37 runs
- Allama Iqbal Express 10DN10علامہ اقبال ایکسپریس 10 ڈائون21:34→00:25 +1d2h 51m24% on time · +1h 11madds 9 min over this leg · 35 runs
- Tezgam 8DN8تیزگام 8 ڈاؤن22:49→01:30 +1d2h 41mno delay figure yetadds 16 min over this leg · 37 runs
Travelling the other way? Rohri Jn. to Rahim Yar Khan trains →
Common questions
How many trains run from Rahim Yar Khan to Rohri Jn.?
13 scheduled services on the current published timetable. That is what is booked to run, not what ran today.
Which is the fastest train from Rahim Yar Khan to Rohri Jn.?
Shalimar Express 28DN, booked at 2h 28m for the journey. That is the timetable's figure. Whether it holds on the day is what the delay columns describe.
Which train from Rahim Yar Khan to Rohri Jn. is most likely to be on time?
Shalimar Express 28DN has the best recorded punctuality of the services we hold enough history for: 39% of its recorded stop arrivals were within 15 minutes of schedule, with a typical delay of 27 min. That is its record across every stop of its full journey, not this leg alone. Measured from recorded runs, not from the timetable. 9 of 13 services on this route currently have enough recorded history to rank at all.
Is there an overnight train from Rahim Yar Khan to Rohri Jn.?
Yes. 3 of the 13 scheduled services are booked to arrive on a later day than they depart: Pakistan Express 46DN, Allama Iqbal Express 10DN, Tezgam 8DN.
Do trains lose time between Rahim Yar Khan and Rohri Jn.?
Typically yes. Rehman Baba Express 48DN adds about 16 min to its delay over this leg, measured across 37 recorded runs. That is the CHANGE over the leg, not how late the train arrives: a train can run late its whole journey and add nothing here.
How far is it from Rahim Yar Khan to Rohri Jn. by train?
It is between 173 and 175 km along the track, depending on the service. Measured by summing our own GPS traces of trains running the route, not the straight-line distance between the two stations, which is always shorter than the rails. That is measured on 11 of the 13 services; the rest of the track on this route has not been traced yet.
Are these Rahim Yar Khan to Rohri Jn. timings the real arrival times?
No. The departure and arrival columns are what the published timetable books. The delay columns beside them are what we recorded actually happening, from the operator's own reports and from GPS traces of the trains. Where a delay figure is blank we do not yet hold enough recorded runs to publish one.